EstimatIing

Estimate of construction of a building consists of two parts

Material Estimate
In this section we have tried to provide some data by which you can have a check on the requirement as well as consumption of the materials.
A)     Dry materials required for one cu.m. of cement concrete
Mix
Cement in 50 kg. bagsSand in cu.m.Aggregate (Stone chips) 20mm to 50mm in cu.m.
1:1 ½ :3
8.09 bags
0.425
0.85
1:2:4
6.37 bags
0.445
0.89
1:2 ½ :5
5.26 bags
0.460
0.92
1:3:6
4.49 bags
0.470
0.94
1:4:8
3.46 bags
0.485
0.97
1:5:10
2.78 bags
0.485
0.97
B)      Materials required for one cu.m. of brick masonry using 25% wet mortar
Mix
Cement in 50 kg. bags
Bricks in Nos.
254mm x 127mm x 76mm size190mm x 90mm x 90mm size
1:2
3.41
335
530
1:3
2.54
335
530
1:4
2.03
335
530
1:5
1.72
335
530
1:6
1.44
335
530
1:7
1.25
335
530
1:8
1.11
335
530
C)      Cement required for 25 mm thick Plaster for ten sq.m. of plaster
Mix
Cement in 50 kg. bags
1:2
4.01
1:3
3.10
1:4
2.48
1:5
2.10
1:6
1.75
 D)     Cement required for 20 mm thick Plaster for ten sq.m. of plaster
Mix
Cement in 50 kg. bags
1:2
3.26
1:3
2.52
1:4
2.01
1:5
1.61
1:6
1.42
 E)      Cement required for 15 mm thick Plaster for ten sq.m. of plaster
Mix
Cement in 50 kg. bags
1:2
2.46
1:3
1.90
1:4
1.52
1:5
1.29
1:6
1.07
 F)      Cement required for 12.7 mm thick Plaster for ten sq.m. of plaster
Mix
Cement in 50 kg. bags
1:2
2.00
1:3
1.54
1:4
1.23
1:5
1.05
1:6
0.87
 G)     Cement required for 10 mm thick Plaster for ten sq.m. of plaster
Mix
Cement in 50 kg. bags
1:2
1.84
1:3
1.42
1:4
1.14
1:5
0.96
1:6
0.80
 H)     Material required for one sq.m. of White washing
Coat
Shell lime in Kg.Quick lime in Kg.
One coat work
0.05
0.10
Two coats work
0.08
0.17
Three coats work
0.12
0.23
 I)        Materials required for one sq.m. of Distempering
Coat
Distemper in Kg.
1st coat
0.122 kg.
2nd and subsequent coats
0.073 kg. Per coats
 J)       Materials required for hundred sq.m. of Varnishing
Coat
Varnish in Litres
One coat work
7.5
Two coats work
12.5
 K)       Rough Estimate of materials for overall building
Materials required on plinth area basis for single storey building
Name of Items
Quantity per sq.m. of plinth area
Bricks500 Nos.
Cement1.5 Bags
Steel bars12 Kg.
Cost Estimate
ROUGH ESTIMATE OF COST OF BUILDINGS
Name of Items
Percentage of total cost
Labour
30     o 35
Cost of materials
65     o 70
Foundation upto and including plinth
15     o 20
Superstructure
80     o 85
Second storey
75 to 85 of 1st storey
Direct and overhead Cost:a)      Direct on actual work
b)      Overhead cost due to establishment, supervision, incidental etc.
85
15
Sanitation and electrificationa)      Sanitary and water supply
b)      Electric installations without fans
c)       Electric fans
7 to 9
7
5
Cost break-up of different partsa)      Earthwork in excavation and filling
b)      Foundation concreting
c)       Damp proof course
d)      Brick work
e)      Roofing
f)       Doors and windows
g)      Plastering and painting
h)      White and colour washing, painting
i)        Miscellaneous
½ to 1
4 to 6
1
34
20
16
10
2
4
Cost of material and laboura)      Bricks
b)      Cement
c)       Steel bars
d)      Timber
e)      Lime
f)       Labour
g)      Miscellaneous
25
10
10
15
5
30
5
Annual repair and maintenance
1 to 1 ½ of capital cost of building