Estimate of construction of a building consists of two parts
Material Estimate
In this section we have tried to provide some data by which you can have a check on the requirement as well as consumption of the materials.
A) Dry materials required for one cu.m. of cement concrete
Mix
| Cement in 50 kg. bags | Sand in cu.m. | Aggregate (Stone chips) 20mm to 50mm in cu.m. |
1:1 ½ :3 |
8.09 bags
|
0.425
|
0.85
|
1:2:4 |
6.37 bags
|
0.445
|
0.89
|
1:2 ½ :5 |
5.26 bags
|
0.460
|
0.92
|
1:3:6 |
4.49 bags
|
0.470
|
0.94
|
1:4:8 |
3.46 bags
|
0.485
|
0.97
|
1:5:10 |
2.78 bags
|
0.485
|
0.97
|
B) Materials required for one cu.m. of brick masonry using 25% wet mortar
Mix
| Cement in 50 kg. bags |
Bricks in Nos.
| |
254mm x 127mm x 76mm size | 190mm x 90mm x 90mm size | ||
1:2
|
3.41
|
335
|
530
|
1:3
|
2.54
|
335
|
530
|
1:4
|
2.03
|
335
|
530
|
1:5
|
1.72
|
335
|
530
|
1:6
|
1.44
|
335
|
530
|
1:7
|
1.25
|
335
|
530
|
1:8
|
1.11
|
335
|
530
|
C) Cement required for 25 mm thick Plaster for ten sq.m. of plaster
Mix
| Cement in 50 kg. bags |
1:2
|
4.01
|
1:3
|
3.10
|
1:4
|
2.48
|
1:5
|
2.10
|
1:6
|
1.75
|
D) Cement required for 20 mm thick Plaster for ten sq.m. of plaster
Mix
| Cement in 50 kg. bags |
1:2
|
3.26
|
1:3
|
2.52
|
1:4
|
2.01
|
1:5
|
1.61
|
1:6
|
1.42
|
E) Cement required for 15 mm thick Plaster for ten sq.m. of plaster
Mix
| Cement in 50 kg. bags |
1:2
|
2.46
|
1:3
|
1.90
|
1:4
|
1.52
|
1:5
|
1.29
|
1:6
|
1.07
|
F) Cement required for 12.7 mm thick Plaster for ten sq.m. of plaster
Mix
| Cement in 50 kg. bags |
1:2
|
2.00
|
1:3
|
1.54
|
1:4
|
1.23
|
1:5
|
1.05
|
1:6
|
0.87
|
G) Cement required for 10 mm thick Plaster for ten sq.m. of plaster
Mix
| Cement in 50 kg. bags |
1:2
|
1.84
|
1:3
|
1.42
|
1:4
|
1.14
|
1:5
|
0.96
|
1:6
|
0.80
|
H) Material required for one sq.m. of White washing
Coat
| Shell lime in Kg. | Quick lime in Kg. |
One coat work
|
0.05
|
0.10
|
Two coats work
|
0.08
|
0.17
|
Three coats work
|
0.12
|
0.23
|
I) Materials required for one sq.m. of Distempering
Coat
| Distemper in Kg. |
1st coat
|
0.122 kg.
|
2nd and subsequent coats
|
0.073 kg. Per coats
|
J) Materials required for hundred sq.m. of Varnishing
Coat
| Varnish in Litres |
One coat work
|
7.5
|
Two coats work
|
12.5
|
K) Rough Estimate of materials for overall building
Materials required on plinth area basis for single storey building
Name of Items
|
Quantity per sq.m. of plinth area
|
Bricks | 500 Nos. |
Cement | 1.5 Bags |
Steel bars | 12 Kg. |
Cost Estimate
ROUGH ESTIMATE OF COST OF BUILDINGS
Name of Items
|
Percentage of total cost
|
Labour |
30 o 35
|
Cost of materials |
65 o 70
|
Foundation upto and including plinth |
15 o 20
|
Superstructure |
80 o 85
|
Second storey |
75 to 85 of 1st storey
|
Direct and overhead Cost:a) Direct on actual work
b) Overhead cost due to establishment, supervision, incidental etc.
|
85
15
|
Sanitation and electrificationa) Sanitary and water supply
b) Electric installations without fans
c) Electric fans
|
7 to 9
7
5
|
Cost break-up of different partsa) Earthwork in excavation and filling
b) Foundation concreting
c) Damp proof course
d) Brick work
e) Roofing
f) Doors and windows
g) Plastering and painting
h) White and colour washing, painting
i) Miscellaneous
|
½ to 1
4 to 6
1
34
20
16
10
2
4
|
Cost of material and laboura) Bricks
b) Cement
c) Steel bars
d) Timber
e) Lime
f) Labour
g) Miscellaneous
|
25
10
10
15
5
30
5
|
Annual repair and maintenance |
1 to 1 ½ of capital cost of building
|